What is a dependency
Also known as: dependencies, task dependency, project dependency
Definition
A task dependency in project management is a link where one task cannot start or finish until another does. It sets the order of work and carries delays.
Why it matters
A dependency is what carries a delay from one task to the next.
Common mistakes
Assuming every link is finish to start, when some tasks can start together or overlap.
Related terms
Worked exampleIllustration
The design approval comes late
On the six week flower shop website, development cannot start until the design is approved, a finish to start dependency.
- +3 days
The design approval comes 3 days late.
- +3 days
Development starts 3 days late, because it waits on the approval.
- +3 days
Testing and the launch move by the same 3 days.
- 0 days
The shop's texts, written alongside, do not move, because nothing waits on them yet.
The arrow is what carries the delay.
Illustration
One late approval, and everything that waits on it
Approved 3 working days late: development, testing and the launch all move by the same amount, into week 7. The texts stay where they were, because nothing waits on them yet.
Definition
PMI describes a dependency as a logical relationship between two activities. There are four types. Finish to start: B starts after A finishes, such as development after the design is approved. It is the most common type. Start to start: B can start once A has started. Finish to finish: B can finish only once A has finished. Start to finish: B can finish only once A has started, which is rare. Two more distinctions help. A mandatory dependency is hard logic that cannot be otherwise, while a discretionary one is a preferred order the team could change. An internal dependency sits inside the team, while an external one, such as a supplier's delivery, does not.
Why it matters
When a task that others wait on slips, everything behind it moves, while a task that nobody waits on can slip without effect. Knowing the links tells you which delays matter, who is waiting on whom, and which blockers (tasks that hold up other tasks) to clear first. Whether a slip moves the finish also depends on float: a task with spare days absorbs it, a task on the critical path does not.
Directly related: Project, Critical Path, Gantt Chart.
Improvement tips
- For each task, ask what must be finished, or started, before it can go ahead.
- Mark external dependencies, such as a supplier's delivery or a customer's approval, and agree their dates in writing.
- Tell mandatory links from discretionary ones: a discretionary link can be changed to save time.
- When a task is late, follow its arrows to see which tasks move with it and which do not.
Common mistakes
- Leaving external dependencies off the plan, so the first sign of a supplier delay is the delay itself.
- Treating a preferred order as unavoidable, and losing time that overlapping could save.
- Updating a late task and forgetting the tasks that wait on it.
Related terms
Project
A project is temporary work with a start and a finish that creates one unique result, such as a new website, within limits of scope, time and cost.
Critical Path
The critical path is the longest chain of dependent tasks in a project. It sets the finish date: a delay on it delays the project, a gain elsewhere does not.
Gantt Chart
A Gantt chart is a schedule in which each task is a horizontal bar on a time scale, so you see what runs together, what waits and when the work ends.
Bottleneck
A bottleneck is the slowest step in a process, the one that sets how much the whole business can deliver. In a small business, it is often the owner.
Quick check
Development waits for the design approval, and the approval is 3 days late. What happens to the texts the shop writes alongside, which nothing waits on?
Choose an answer
Frequently asked questions
Do I need to think about dependencies when starting my business?
When does a new business first run into task dependencies?
How do I map dependencies for my business launch?
How does understanding dependencies save a new business money?
Why do dependencies matter for a business already running?
What goes wrong when a business owner ignores task dependencies?
How do I start tracking dependencies without stopping daily work?
How do I manage dependencies that rely on outside suppliers?
What does dependency mean in plain business words?
Is tracking dependencies risky or complicated?
Do I need a project management expert to find dependencies?
What happens if a task that many others depend on is delayed?
Sources: PMI, A Guide to the Project Management Body of Knowledge (PMBOK Guide), PMI, Lexicon of Project Management Terms
Last reviewed: 2026-09-24
I have worked with
- Google for Startups
- House of Business, Sderot Municipality
- Microsoft Reactor
- GameReady
- Eclipse Capital
- SderoTech
- IUCEL
- Resilience & Health Innovation Hub
- International Resilience Institute of Sderot
- Google for Startups
- House of Business, Sderot Municipality
- Microsoft Reactor
- GameReady
- Eclipse Capital
- SderoTech
- IUCEL
- Resilience & Health Innovation Hub
- International Resilience Institute of Sderot
What Clients Say
From different fields, at different stages of business
Dan Manto
Eclipse Capital
Real Estate Investment and Finance, USA
Arty McLabin
GameReady
Game Development Education and Outsourcing, International

Anna
Beautician
After I finished a cosmetology course at a leading company, I was confused. I didn't know how to open a business, what to sell from home, or how to bring in clients. Since I reached out to Mobius, everything has changed. We built an organized plan with clear steps and no unnecessary risks. Today I see results, and I'm growing and developing every month.

Mark
Massage therapist, Gan Yavne
When I finished a massage course, I imagined a different world. I found out it's a hard field, and financial stability isn't easy to find. When I came to Mobius, something changed. We started an organized process and built a business plan. Without Mobius? I probably would have given up. Today I believe in myself and in my own path.
Projects always running late or over budget?
Alex helps Israeli businesses deliver projects on time and on plan. The first call is free.
+972 055-248-6151. Better on WhatsApp: I am in meetings most of the day and answer as soon as I am free. Other ways to reach me